Hi there! I'm looking for some guidance on how to automatically create tasks based on the start and end date of my Epic.
Each Epic represents a project that we need to have 25%, 50%, and 75% check-ins on. I want a task built once we hit 25% into the campaign, 50% into the campaign and 75%. The logic would be (((Campaign End Date - Campaign Start Date) +1)*.25)+Campaign Start Date)) is the date we'd want the ticket built on. Repeat for 50% and 75%.
I do not want these tickets dependent on a workflow change, because no workflow status change will occur at these intervals.
Thoughts or suggestions of add-ons to purchase, if needed?