I created a custom board to filter my tasks only for the active sprint. everytime, i need to refresh the sprint in the board. is there a constant that refers the active sprint so that I don't need to change everytime sprint advances?
Hi @Mahadevan Hariharan Project = "test project" AND sprint in openSprints()Note: Replace test project with your project name. Hope this helpsRegards
You can fine tune more with following Statement and so on, Project = "test project" AND sprint in openSprints() AND resolution = unresolved Note: Replace test project with your project name & use resolution key as per your terminology . It may be pending, unresolved , tobetaken anything. Kindly use accordingly .Regards
Thanks! it works. openSprints() only works with "in" and not with "-"
When I use this query it does not pull in any user stories or tasks that have rolled over from previous sprints. How do I include those in my query?
Thanks, @Haran Kumar This was very helpfully.
This doesn't actually reference the current sprint. It references all open sprints. This can be an issue if you create a sprint early for staging, but you don't start the sprint until it's ready to go.
We can also try below Jql query, here we have removed closedSprint - the previous completed sprints & the future sprints. This Jql query gives you stories part of active sprint.issuetype = Story AND Sprint not in (closedSprints(), futureSprints())
this also excludes items rolled over from previous sprint. anyone have any solutions for this? As we are planning a full quarter as per scaled agile, future sprints are populated to some degree, but we also have some level of rollover. Any ideas? thanks