Hi,
Is it possible to execute bulk update using excel file like this?
(Assumption: requirement proposal date, spec discussion date, systems review date are defined in Jira already.)
| Issue Key | Issue ID | Requirement Proposal | Spec Discussion | Systems Review |
| MSADCC-3393 | 428141 | 1/21/2019 | 3/4/2019 | 3/11/2019 |
| MSADCC-3427 | 428175 | 2/25/2019 | 4/15/2019 | 4/22/2019 |
| MSADCC-3428 | 428176 | 2/25/2019 | 4/15/2019 | 4/22/2019 |
| MSADCC-3431 | 428179 | 1/21/2019 | 3/4/2019 | 3/11/2019 |
| MSADCC-3432 | 428180 | 1/21/2019 | 3/4/2019 | 3/11/2019 |
| MSADCC-3433 | 428181 | 3/18/2019 | 4/15/2019 | 4/22/2019 |
| MSADCC-3434 | 428182 | 3/11/2019 | 4/8/2019 | 4/15/2019 |
| MSADCC-3435 | 428183 | 1/0/1900 | 1/0/1900 | 1/0/1900 |
| MSADCC-3464 | 428212 | 2/13/2019 | 3/18/2019 | 3/20/2019 |
| ... | ... | ... | ... | ... |
I know it can't be done using bulk update screen.
I was trying scripting, but can't find appropriate template yet.
Thanks, Teru