We are running v7.11 with structure, no other add ons, our guys are estimating their time and loggin work on the sub-tasks, which is rolling up correctly to the tasks.
However, in our structure view when I add a columb for 'Σ Original Estimate' it will not show all tasks as having estimates. (the sum of sub-items box is ticked)
How can I get structure to show these?
Its the same when I run a JQL search with 'originalEstimate = EMPTY' it shows tasks I know how sub-tasks with estimates and time logged.
Any help would be good.
Edit:
My issue is very much the same as this one: https://community.atlassian.com/t5/Jira-questions/Find-issues-with-no-estimates-including-calculated-Remaining/qaq-p/990300
However I do not have Script Runner,