Hi there

I would like to export a PDF of the Gantt chart that includes completion tick and duration (original estimate). Is this possible at all? I don't see the option for those in the settings for export.

Thanks

1 answer

0 votes
Mario O.G
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
October 18, 2018

Hi Camille,

How are you?

For now, it is only possible to export the Issue Key & the Summary.

However, the idea of including the possibility of exporting different fields, such as Status and Original Estimate is already in our backlog, and we'll be evaluating where this fits into our roadmap.

I'll make sure to post an update on your question when it becomes available.

(Thank you for using Structure).

Mario O.G

[ALM Works]

Camille
Contributor
January 1, 2019

Hi Mario, is there any update on this feature yet? We desperately need the completion status added to the Gantt Chart export PDF.

Camille
Contributor
January 1, 2019

This could actually be better viewed if it simply changes the colours of the Gantt bar according to the status (green = done), instead of using blue everywhere.

Mario O.G
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
February 13, 2019

Hi Camille, 

My apologies about the late reply.

We'll probably be releasing the possibility of exporting different fields, after the release of version 2.0.  (I'll be voting to raise the priority of this task).

As for the ability to change the bar color according to status, you should be able to achieve that by creating and customizing a slice of the Gantt chart configuration.

Creating a Slice: https://wiki.almworks.com/x/rh50Aw

Let me know if you need anything else.

Mario O.G

[ALM Works]

Like Camille likes this
joehardin
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
April 13, 2024

@Mario O.G I have the same need: ability to include additional columns in the gantt export. Assuming the OP was referring to Cloud, it's been 5 years - this has to be on the dev list soon, right?

Like Steven Baynes likes this
Steven Baynes May 3, 2024

Also, looking to include additional columns in the gantt export