We're developing a new product that consists of two parts. The two parts will be released in two separate releases. Let's say release A is for our current development work and release B is for the next iteration.
For the new product I've created a initiative. If in 'plans' I select that initiative and filter on the current release (A), the timeline still shows epics related to the next release (B).
The epics that are releated to release B are greyed out, but the timeline of the initiative is determined by the epic that has the latest due date (which is an epic in release B).
Can I somehow show only the timeline for release A of a specific initiative? That way I know whether the work on the initiative, that is planned for in release A cycle, will be finished on time