How do I link a task (not a sub-task) to a parent task?

Riccardo Zaniboni
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
September 4, 2017
I need to create a parent task, and then I will have to clone it many times and have it in the backlog but under different epics (all the cloned tasks have to be linked to the original parent task, that has to appear still in the backlog, under another epic)

1 answer

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

Post a new question

0 votes
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
September 4, 2017

You can use issue links (cloning issues will do that automatically, linking the new issue back to its source), but these will not be parent/child relationships like you get from sub-tasks.