Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Deleted user
0 / 0 points
Next:
badges earned

Your Points Tracker
Challenges
Leaderboard
  • Global
  • Feed

Badge for your thoughts?

You're enrolled in our new beta rewards program. Join our group to get the inside scoop and share your feedback.

Join group
Recognition
Give the gift of kudos
You have 0 kudos available to give
Who do you want to recognize?
Why do you want to recognize them?
Kudos
Great job appreciating your peers!
Check back soon to give more kudos.

Past Kudos Given
No kudos given
You haven't given any kudos yet. Share the love above and you'll see it here.

It's not the same without you

Join the community to find out what other Atlassian users are discussing, debating and creating.

Atlassian Community Hero Image Collage

Jira Structure Gantt Chart

Hello,

I have created a Jira Structure Gantt chart and the data is created using a Jquery. The challenge is that when i do the changes in one of my stories these changes doesn't reflect in my Gantt Chart graph, but it does reflect in the details part on right side. I am not sure why it is not getting reflecting or sync from jira to chart. Any help will be highly appricicated.

1 answer

Hello,

When tasks are scheduled automatically - i.e. the scheduling dates are calculated by Structure.Gantt and these dates are not taken directly from Jira fields - then they only exist as attributes on the Gantt chart. That's why they are displayed on the chart and in the task's details window but not in Jira.

If you want the scheduling changes to be reflected in Jira, the scheduling can be done manually - in this case, Start & Finish Dates are defined by Jira fields and the data is synchronized between the fields and the Gantt chart. Manual scheduling can be defined in the Gantt chart's configuration - you need to open it, edit it and then select fields for scheduling dates in the Scheduling tab. You can find more about it in our documentation:
https://wiki.almworks.com/display/gantt/Manual+Scheduling+by+Start+or+Finish+Date

And if the scheduling is done automatically, you can show the calculated attributes in corresponding Structure columns - Gantt Start/Finish Dates, - and you can also write these attributes to Jira fields using Effectors.
https://wiki.almworks.com/display/structure/Attribute+to+Issue+Field+Effector

I hope this helps. If you need further assistance, please feel free to contact us at support.almworks.com and we'll take a look at your use-case and provide you with more detailed instructions depending on what you're trying to achieve.

Best regards,
Stepan Kholodov
ALM Works

Suggest an answer

Log in or Sign up to answer
TAGS
Community showcase
Published in Team-managed projects

4 steps to get actual statuses on the Jira board.

Jira   is a powerful tool   that helps teams to plan, manage, and report on their work.   We love using Jira, especially for its ability to track issue progress. But how to monitor the...

1,199 views 10 14
Read article

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you