How do I associate an active Sprint Board to an active Sprint?

I am a Jira user. I have an active sprint but the board created from a filter does not seem to be associated to my project. This being the case the Issues from the Sprint are displayed on the board.

I was told my Sprint board is not associated to my project because they do not have the same project image. Additionally when I am in the project the board does not display from the ellipsis.

1 answer

0 vote

Boards do not have a direct relationship with projects.  It's indirect, where a board has a filter that includes a project - that's the only link between them and it can change.

A sprint belongs to a board.  So if your board does not include a project, that project does not have anything to do with a sprint.

Start with a look at the board - what, exactly, does the board filter say?  (No need to give us the definition, but you need to be 100% sure that the filter includes the project you are missing from the board)

Suggest an answer

Log in or Sign up to answer
How to earn badges on the Atlassian Community

How to earn badges on the Atlassian Community

Badges are a great way to show off community activity, whether you’re a newbie or a Champion.

Learn more
Community showcase
Posted Tuesday in Uncategorized

Friday fun: how many celebrates Midsummer holiday or is this a Swedish tradition only?

Any other country that celebrates Midsummer holiday (this friday 22 June)?  

44 views 3 1
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you