change "Working hours per day" by a decimal value

Dear all,

on Jira cloud application, in the "time tracking configuration" screen, I am trying to change the "working hours per day" from 8 to 8.5 hours.

I can save the new value, which is updated on the time tracking configuration screen.

But the new value is not really taken into account by Jira and when I refresh the time tracking configuration screen, the value by default (8 hours) is back.

do you have a solution ?

Thanks a lot

1 answer

1 accepted

This widget could not be displayed.

after investigation, the number of hours shown in the configuration screen is wrong. The new value has been taken into account

Suggest an answer

Log in or Sign up to answer
Atlassian Summit 2018

Meet the community IRL

Atlassian Summit is an excellent opportunity for in-person support, training, and networking.

Learn more
Community showcase
Posted Wednesday in New to Jira

Are you planning to trial, or are currently trialling Jira Software? - We want to talk to you!

Hello! I'm Rayen, a product manager at Atlassian. My team and I are working hard to improve the trial experience for Jira Software Cloud. We are interested in   talking to 20 people planning t...

113 views 2 0
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you