change "Working hours per day" by a decimal value

Dear all,

on Jira cloud application, in the "time tracking configuration" screen, I am trying to change the "working hours per day" from 8 to 8.5 hours.

I can save the new value, which is updated on the time tracking configuration screen.

But the new value is not really taken into account by Jira and when I refresh the time tracking configuration screen, the value by default (8 hours) is back.

do you have a solution ?

Thanks a lot

1 answer

1 accepted

Accepted Answer
0 votes

after investigation, the number of hours shown in the configuration screen is wrong. The new value has been taken into account

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Sep 25, 2018 in Jira

Atlassian Research Workshop opportunity on Sep. 28th in Austin, TX

We're looking for participants for a workshop at Atlassian! We need Jira admins who have interesting custom workflows, issue views, or boards. Think you have a story to sha...

418 views 7 5
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you