Why is there a random sprint created between my sequential sprints created in Jira Agile

Hi, the sprint "06 - 19 Sep" is randomly scheduled between two sequential sprints created in Jira. If I move one story out, more take its place.

It seems like Portfolio is seeing open time between the 10th of December and 23 December, even though I have scheduled a sprint.

image2016-12-6 8:9:16.png

 

Please advise urgently.

 

1 answer

1 accepted

Hi, 

 

We found the answer to the problem. The sprint existed on a project that was "hidden" by being assigned to a permission scheme that was not assigned any permissions. Once we traced the sprint id and project using the issue search, we were able to access the project and delete the sprint, solving the problem.

Suggest an answer

Log in or Sign up to answer
Atlassian Community Anniversary

Happy Anniversary, Atlassian Community!

This community is celebrating its one-year anniversary and Atlassian co-founder Mike Cannon-Brookes has all the feels.

Read more
Community showcase
Julia Dillon
Posted Tuesday in Jira

Tell us how your team runs on Jira!

Hey Atlassian Community! Today we are launching a bunch of customer stories about the amazing work teams, like Dropbox and Twilio, are doing with Jira. You can check out the stories here. The thi...

243 views 1 18
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you