Hi, the sprint "06 - 19 Sep" is randomly scheduled between two sequential sprints created in Jira. If I move one story out, more take its place.

It seems like Portfolio is seeing open time between the 10th of December and 23 December, even though I have scheduled a sprint.

image2016-12-6 8:9:16.png

 

Please advise urgently.

 

1 answer

1 accepted

Hi, 

 

We found the answer to the problem. The sprint existed on a project that was "hidden" by being assigned to a permission scheme that was not assigned any permissions. Once we traced the sprint id and project using the issue search, we were able to access the project and delete the sprint, solving the problem.

Suggest an answer

Log in or Sign up to answer
How to earn badges on the Atlassian Community

How to earn badges on the Atlassian Community

Badges are a great way to show off community activity, whether you’re a newbie or a Champion.

Learn more
Community showcase
Published Sunday in Agility

You asked for it, so we delivered: images on issues have arrived

A picture tells a thousand words. And agility boards have just released their latest feature: cover images on issues – so now your board can tell a story at first glance. Upload attachmen...

184 views 1 11
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you