Start and/or End Date driven by time estimate?

Is there a way to involve the time estimate in the creation of the Gantt chart? That is, if a user estimates 16 hours for a story, how can that automatically generate a bar on the Gantt chart that is 2 days long?

1 answer

Hello David,

 

In some cases this would depend on the plugin which you use (either BigPicture's Gantt module or BigGantt), though generally this calculation is made by the plugin based on the pre-determined settings in Jira's Administrative panel. 

 

TT.png

 

Once we set the Time Tracking for a business week to be 5 days and the business day to be 8 hours, this calculation will be made automatically and your 16h story will be split into 2 business days. 

 

Kind Regards,

Piotr of SoftwarePlant

@Piotrek Romanczyk [SoftwarePlant] So then it will make the end of the bar the Due Date and the start of the bar the (Due Date - Time Estimate)?

Also, it's a bummer that many of these settings are per JIRA instance - my company has an instance shared with hundreds of people so there are many subgroups that operate very differently and we usually can't just change fields like the ones your suggesting for everyone.

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Sep 18, 2018 in Jira

What modern development practices are at the heart of how your team delivers software?

Hey Community mates! Claire here from the Software Product Marketing team. We all know software development changes rapidly, and it's often tough to keep up. But from our research, we've found the h...

23,955 views 2 7
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you