Kanban Project Management | Sequencing issues based on start and end date

One of my PMs asked if there is a way to sequence tasks in a kanban project. The PM wants to have a start date and an end date for each task. I know i can create custom..question is also if I should use due date as the end date.

also the PM wants (this is the main thing) to be able to change the date on one task, and all tasks that were following it should change the dates accordingly. so this way, the whole remaining body of work within the epic would move forward in time automatically.

1 answer

0 vote
Alexey Matveev Community Champion Nov 17, 2017

Hello,

In my opinion you should use DueDate.

About the other question the PM wants to have something similair to Microsoft Project. You should look at the plugin called BigPicture. 

https://marketplace.atlassian.com/plugins/eu.softwareplant.bigpicture/cloud/overview

you are right, the PM got the idea from Microsoft Project. Thank you for this insight!

Suggest an answer

Log in or Sign up to answer
Atlassian Community Anniversary

Happy Anniversary, Atlassian Community!

This community is celebrating its one-year anniversary and Atlassian co-founder Mike Cannon-Brookes has all the feels.

Read more
Community showcase
Posted 13 hours ago in Jira

We want to know what Jira Service Desk apps you're using!

Hi Community! My name is Amir and I’m on the Jira Service Desk product marketing team at Atlassian. Our team would love to understand how you’re leveraging our ecosystem for Jira Service Desk. Wha...

36 views 0 5
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you