Jira velocity chart includes sprint from another board

Elmarie Potgieter May 22, 2017

I have 2 Jira boards, let's call them Team A and Team B.

The Velocity Chart for Team A includes a sprint for Team B, for no apparent reason.

The incorrect sprint shows zero committed and zero completed on the Team A Velocity Chart, however it shows correctly on the Team B board's Velocity Chart.

When I click on the incorrect (Team B) sprint on the Team A Velocity Chart, it shows details for one of the Team A sprints.

I have re-indexed both projects but that did not make a difference.

How can I remove the incorrect sprint from Team A's Velocity Chart?

 

2 answers

0 votes
Vincent Lyon May 22, 2017

Hi,

I had the same issue while configuring a new board for a new team. This means that you have issues from the other board in your backlog.

What I did was just filter the issues by component :

  1. Add components "Team A" and "Team B"
  2. Set the components to your issues
  3. Then in the general filter of
  • Board A : component = "Team A"
  • Board B : component = "Team B"

And voilà ! (if I dare say)

Just note that this works only if no issue is in both boards (ex: issue n°14 is in board A and Board B)


I hope this helped you !

Regards,

Vincent

Elmarie Potgieter May 23, 2017

Thanks very much Vincent! Will give this a try.

Regards,

Elmarie

0 votes
Pedro Felgueiras
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
May 22, 2017

Filter by the sprint of Team B and check if it have any issue that belongs to Team A 

Suggest an answer

Log in or Sign up to answer