Jira Timesheet plugin not linked to projects

JIRA v 5.2.10
TimeSheet plugin 2.7.5

If we go on projects in Jira choose a project and then choose "Time Sheet Report". The field "Project" is by default blank and needs to be filled out manually. We didin't have to do that earlier (before upgrading JIRA to v 5.2.10). It looks almost that the plugin has lost it's link to the projects. How do we get JIRA to choose the chosen project automaticly ?

2 answers

I think JIRA restart should help, project parameter should be 'projectid', not 'project' - that's why it's ignored. It must have changed recently in report configuration.

I've just tried on 5.2.11 and it works fine, does your url have similar parameters as the following?

selectedProjectId=10100&projectOrFilterId=project-10100&projectOrFilterName=Test%20Project

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Nov 27, 2018 in Portfolio for Jira

Introducing a new planning experience in Portfolio for Jira (Server/DC)

In the past, Portfolio for Jira required a high degree of detail–foresight that was unrealistic for many businesses to   have–in   order to produce a reliable long-term roadmap. We're tur...

2,941 views 19 22
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you