If i change the sprint name/dates in one project it is reflected in another project as well.

We have two projects. Android and Backend. When we create the sprint and change the name in Android project the sprint name changes in Backend project as well. We create one sprint in Backend , it gets reflected in Android project as well. 

Can you please help?

2 answers

This widget could not be displayed.

U mean sprint(name/date) share other projects???

This widget could not be displayed.

Sprints do not belong to projects, they belong to boards.

If your board happens to include several projects, then there's still only one sprint there, so when you change it, of course it "changes in the other projects" - there's one single sprint.

Suggest an answer

Log in or Sign up to answer
Atlassian Summit 2018

Meet the community IRL

Atlassian Summit is an excellent opportunity for in-person support, training, and networking.

Learn more
Community showcase
Posted yesterday in New to Jira

Are you planning to trial, or are currently trialling Jira Software? - We want to talk to you!

Hello! I'm Rayen, a product manager at Atlassian. My team and I are working hard to improve the trial experience for Jira Software Cloud. We are interested in   talking to 20 people planning t...

78 views 1 0
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you