Export to excel formatting issues

When exporting to excel the original estimate, remaining estimate and time spent fields are not formatted correctly. using JIRA 4.4 excel 2010.

1 w in original estimate when exported to excel is represented as 144000.

2 answers

1 accepted

This widget could not be displayed.

40hrs * 60 minutes * 60 seconds = 144000

I'm not sure if that can be changed.

of course, it converts the weeks, days, hours to seconds for consistent exporting. Thank You

This widget could not be displayed.

You can use the Better Excel Plugin to do this conversion for you. You can both use an Excel formula and Excel's cell formatting for this. 

If you export time values frequently, it will save you from a lot of repetitive work.

Suggest an answer

Log in or Sign up to answer
Atlassian Summit 2018

Meet the community IRL

Atlassian Summit is an excellent opportunity for in-person support, training, and networking.

Learn more
Community showcase
Posted Wednesday in New to Jira

Are you planning to trial, or are currently trialling Jira Software? - We want to talk to you!

Hello! I'm Rayen, a product manager at Atlassian. My team and I are working hard to improve the trial experience for Jira Software Cloud. We are interested in   talking to 20 people planning t...

165 views 2 0
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you