I am using parallel Sprints and I am trying to close one Sprint that its stories are in Done Status but i can't find the choice to do so.. Any idea?

 

Screen Shot 2018-03-29 at 14.38.27.png

1 answer

1 accepted

1 vote
Answer accepted
Warren Community Leader Mar 29, 2018

Hi Vasilis

what you're showing is the backlog - you can't close a sprint from the backlog. You need to go to the active sprint view, then have the sprint showing that you want to close. There should be a Close Sprint button on the top right

Abhi I'm New Here Sep 09, 2019

I closed one sprint out of three that I am running. But I am not able to close the other two sprints I was having along with the one I marked as completed.

 

I am neither able to view the option to close sprint for the other two sprints.

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted in Jira

Demo Den Ep. 7: New Jira Cloud Reports

Learn how to use two new reports for next-gen projects in Jira Cloud:  Cumulative flow diagram and Sprint burndown chart. Ivan Teong, Product Manager, Jira Software, demos the Cumulative ...

335 views 1 3
Join discussion

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you