Cannot clear value in custom field (Date Picker) Start date / End date

Issue mostly described in the summary.

If I try to clear values for Start date and End date (Start date field used by SoftwarePlant plugins). When I clear the value on Edit-Screen it disappears from the view. If I go to 'Edit' page I see that the fields are again filled automatically with the same date as for End date.

It seems that it is not clearing in Database instead of it fetches data fro database and refill.

Described with Screenshots:

Inital phase

1.JPG

Date deleted (disappeared as expceted)

2.JPG

By click on "Edit"

3.JPG

I tried than to delete both. After saving it was refilled with some random dates from the past like Start date: 13.01.2020 End date: 06.06.2020

 

Can someone help please

1 answer

0 votes

Hi @Semih Hotan

Due to inline editing, you can change Start and End Date directly in BigPicture/BigGantt. Changes will be reflected in Jira immediately.

image (3).png

Suggest an answer

Log in or Sign up to answer
TAGS

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you