Can sub-tasks be on a different sprint from the parent task?

Beth Zimmerman
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
April 21, 2016
 

2 answers

1 accepted

0 votes
Answer accepted
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
April 21, 2016

No.

The point of a sub-task is that it is part of the parent task.  So if the parent task is pulled into a sprint, it's nonsense to try to put its parts into another sprint.   If you find yourself wanting to do this, then you need to split up your parent tasks better.

0 votes
Beth Zimmerman
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
April 21, 2016

Thanks for confirming.