JQL query for a Work Week

I need a JQL query to show all issues that were update within a work week, Monday through Friday. I've tried different combinations of the startofweek and startofday but I cannot seem to get it work.

Thanks

 

1 answer

1 accepted

1 vote
Accepted answer

You can use startOfWeek(1d), endOfWeek(-1) and so on, depending on your work week. 

For example:

updated >= startOfWeek(1d) and updated < endOfWeek(-1d)

So 1d is Monday and -1d is Friday? Im not sure how that is

1d is one day from start of week. 2d is 2 day after start of week and so on. Similarly -1d is 1 day before end of week. 

Thank you! makes sense

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Jan 08, 2019 in Jira

How to Jira for designers

I’m a designer on the Jira team. For a long time, I’ve fielded questions from other designers about how they should be using Jira Software with their design team. I’ve also heard feedback from other ...

830 views 3 9
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you