I need a JQL query to show all issues that were update within a work week, Monday through Friday. I've tried different combinations of the startofweek and startofday but I cannot seem to get it work.

Thanks

 

1 answer

1 accepted

0 votes

You can use startOfWeek(1d), endOfWeek(-1) and so on, depending on your work week. 

For example:

updated >= startOfWeek(1d) and updated < endOfWeek(-1d)

So 1d is Monday and -1d is Friday? Im not sure how that is

1d is one day from start of week. 2d is 2 day after start of week and so on. Similarly -1d is 1 day before end of week. 

Thank you! makes sense

Suggest an answer

Log in or Join to answer
Community showcase
Teodora [Botron]
Published Feb 15, 2018 in Marketplace Apps

Jira Inferno: The Nine Circles of Jira Administration Hell

If you spend enough time as a Jira admin - whether you are managing a single, mid-sized instance, a large enterprise one or juggling multiple instances at once - you will eventually find yourself in ...

1,032 views 6 18
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you
Atlassian Team Tour

Join us on the Team Tour

We're bringing product updates and pro tips on teamwork to ten cities around the world.

Save your spot