How to correct logged hours for a user story?

Rajesh Arvapalli September 30, 2020

By mistake I logged 32 hours instead of 16 hours for a user story in JIRA software project in acsjira. Can you let me know on how can I correct it to 16 hours?

1 answer

0 votes
Bastian Stehmann
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
September 30, 2020

Hi @Rajesh Arvapalli ,

 

welcome to the community.

You can do this by editing the worklog. You can find the worklog at the bottom of the issue detail view on the worklog-tab.

But it depends on the permissions, if you are allowed to edit your own worklog or not. If there is no edit-button at the worklog, you are not allowed to change this.

In that case, you will have to ask someone who has this permission. You can probably ask your project lead, he might be able to do that or know someone who does.