How can I change the Sprint report graph to show Story Points instead of hours. I can't find any option that would allow me to do it.

This question is in reference to Atlassian Documentation: Viewing the Sprint Report

Ask your question here...

1 answer

1 accepted

This widget could not be displayed.

Go to board configuration and change the estimation statistic to Story Points.

 

Estimation Statistic was already set to "Story Points", however Time Tracking is set to:

"Remaining Estimate and Time Spent

Track time against issues using JIRA's Remaining Estimate and Time Spent fields." which is probably why the report displays hours. 
Thanks!

Suggest an answer

Log in or Sign up to answer
Atlassian Summit 2018

Meet the community IRL

Atlassian Summit is an excellent opportunity for in-person support, training, and networking.

Learn more
Community showcase
Posted 14 hours ago in New to Jira

Are you planning to trial, or are currently trialling Jira Software? - We want to talk to you!

Hello! I'm Rayen, a product manager at Atlassian. My team and I are working hard to improve the trial experience for Jira Software Cloud. We are interested in   talking to 20 people planning t...

41 views 1 0
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you