How can I change the Sprint report graph to show Story Points instead of hours. I can't find any option that would allow me to do it.

This question is in reference to Atlassian Documentation: Viewing the Sprint Report

Ask your question here...

1 answer

1 accepted

1 vote
Accepted answer

Go to board configuration and change the estimation statistic to Story Points.

 

Estimation Statistic was already set to "Story Points", however Time Tracking is set to:

"Remaining Estimate and Time Spent

Track time against issues using JIRA's Remaining Estimate and Time Spent fields." which is probably why the report displays hours. 
Thanks!

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Tuesday in Statuspage

Introducing Statuspage Getting Started guides! First up: What is Statuspage?

Over the next several weeks we'll be sharing some of our Getting Started guides here in the community. Throughout this series of posts, we'd love to hear from customers and non-customers ab...

227 views 4 1
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you