Hello,
Make sure that the Resolution field is not empty for the issues.
In this sprint we have:
3 issues in To Do. Resolution unresolved. Story points combined = 10
5 issues in In Progress. Resolution unresolved. Story points combined = 12
7 issuses in Done (completed) and Resolution is set to Done. Story points combined = 8
What can we expect the burn down to show here?
If 7 issues with the resolution done are in the most right column of your board, then you will have 8 story points burn down.
Well, as you can see in the above picture on the burndown - this is not showing this
In the sprint report.png you can see that we have finished 496, 510, 554, 555, 584.In table.png you can see that all of these are in the sprint from the sprintstart, this without any Event types has occured, except for 584 (this one has a scope change because its added in the sprint).In table.png we expext to see a new row for every issue that's finished.Even in burndown report.png You can see that the line does not drop/change even thought issues are finished.
It looks like you're new here. Sign in or register to get started.