story point per assignee for a team

manish a
Contributor
October 8, 2023

I want to see consolidated view of story points assignee wise for a team for all the sprint in a pi or for current and next 2 sprints. where can i see that. 

 

 

 

1 answer

1 accepted

2 votes
Answer accepted
Peter Jessen
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
October 9, 2023

@manish a -

Jira Align is an enterprise agile platform, as such it follows agile practices.

Story points are by team, never by individual. You won't a "story point per assignee" metric in any real agile tool or platform, it simply doesn't exist because the agile umbrella (including scrum and kanban) is a team-based methodology, not an individual-utilization-based methodology like traditional PMP waterfall. 

Regards,
Peter

manish a
Contributor
October 9, 2023

there are certain people in the team whose skillsets are critical and therefore within the team we want to understand when these people will be free in future sprints. 

Tom O'Connor
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
October 10, 2023

This would likely fall under how you track capacity at the team level for individuals sprint by sprint. 

So for example you can set an individual to be 100% dedicated to a team, but set capacity for each sprints.  So maybe that person will be 50% dedicated to their team in Sprint 2 and 3 and the other 50% on another team for those sprints.  

https://help.jiraalign.com/hc/en-us/articles/115003641568-10X-Capacity-Planning