I am using "Jira Software" product > "Team-managed Project" Scrum. I opened the Backlog & have full admin access. How to add (or replace) displayed views. I want to add Start date & due date same place as the red question marks - see attached screen shot.

 

Backlog View.png

1 answer

0 votes
Vinay Sharma December 14, 2021

@Amr Darwish You can do it via Board settings. Open the Scrum or Kanban Board of the required project, click on the 3 dots (...) top-right-hand side->Board settings->Card layout, then under backlog, search for "Start date" & "Due date" and add these one-by-one. 

Make sure, "Start date" and "Due date" are also added on the screen via project settings. In order to display these, you need to have these fields filled in.