Missed Team ’24? Catch up on announcements here.

×
Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in

How to configure Backlog view to display start date & due date?

Amr Darwish
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
December 14, 2021

I am using "Jira Software" product > "Team-managed Project" Scrum. I opened the Backlog & have full admin access. How to add (or replace) displayed views. I want to add Start date & due date same place as the red question marks - see attached screen shot.

 

Backlog View.png

1 answer

0 votes
Vinay Sharma December 14, 2021

@Amr Darwish You can do it via Board settings. Open the Scrum or Kanban Board of the required project, click on the 3 dots (...) top-right-hand side->Board settings->Card layout, then under backlog, search for "Start date" & "Due date" and add these one-by-one. 

Make sure, "Start date" and "Due date" are also added on the screen via project settings. In order to display these, you need to have these fields filled in.

Suggest an answer

Log in or Sign up to answer
TAGS
AUG Leaders

Atlassian Community Events