Count open tasks on macro "Task Report" up to a specific due date

Hello,

Anyone knows if it is possible to count open tasks up to a specific Due Date.  I tested some scripts but they just count the open/closed tasks on a page.

Regards,

João

1 answer

Hello João,

Yes it is possible. You'll need to use combination of Table Filter and Pivot Table macros to achieve the goal (Table Filter and Charts add-on).

The structure should be Pivot Table -> Table Filter -> Task Report.

Table Filter: add Date Filter for the due date column and set a specific date or date range. You'll get a filtered table with actual data.

Pivot Table: select Description field in Row Labels field.

 So you can get something like this:2017-06-07_13h40_43.png

Suggest an answer

Log in or Sign up to answer
How to earn badges on the Atlassian Community

How to earn badges on the Atlassian Community

Badges are a great way to show off community activity, whether you’re a newbie or a Champion.

Learn more
Community showcase
Published 5 hours ago in Confluence

Three common content challenges + how to manage them

An efficient enterprise content management system, or ECM, is a must-have for companies that create work online (cough   cough, all companies). If content calendars, marketing plans, and bu...

18 views 0 3
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you