Count open tasks on macro "Task Report" up to a specific due date

Hello,

Anyone knows if it is possible to count open tasks up to a specific Due Date.  I tested some scripts but they just count the open/closed tasks on a page.

Regards,

João

1 answer

This widget could not be displayed.

Hello João,

Yes it is possible. You'll need to use combination of Table Filter and Pivot Table macros to achieve the goal (Table Filter and Charts add-on).

The structure should be Pivot Table -> Table Filter -> Task Report.

Table Filter: add Date Filter for the due date column and set a specific date or date range. You'll get a filtered table with actual data.

Pivot Table: select Description field in Row Labels field.

 So you can get something like this:2017-06-07_13h40_43.png

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Monday in Confluence

Why start from scratch? Introducing four new templates for Confluence Cloud

Hi my Community friends!  For those who don't know me, I'm a product marketer on the Confluence Cloud team - nice to meet you! For those of you who do, you know that I've been all up in your Co...

361 views 2 5
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you