Portfolio for Jira issues not syncing

Christian Sulton
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
August 13, 2018

I'm new to portfolio for jira so bare with me if this is a dumb question, but are the issues created in Portfolio-for-jira supposed to link back to the project in Jira?

Any issue that I make in the project automatically imports to portfolio, but it does not work the other way around. 

I guess I can multiple projects linking up to a portfolio but, I don't see what benefit being able to create issues in portfolio offers if they can't be tied to a project. 

So in short:

Is there a way to tie issues created in the latest verision of portfolio for jira back to a project

1 answer

0 votes
Ryan Fish
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 14, 2018

@Christian Sulton

Look near the top left next to your portfolio title. There is an orange #n uncommitted changes notification. Select and commit/ revert changes to update JIRA. 

Christian Sulton
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
August 14, 2018

That worked perfectly. Thank you!

Ryan Fish
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 16, 2018

 I'm glad to help! Please accept the answer so the question is closed.