Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Come for the products,
stay for the community

The Atlassian Community can help you and your team get more value out of Atlassian products and practices.

Atlassian Community about banner
4,456,374
Community Members
 
Community Events
176
Community Groups

Ignore team capacity when auto-scheduling

Edited

When auto-scheduling, a number of factors are considered including team capacity. I'm hoping to auto schedule based on task dependencies and estimated durations (days) only. Is this possible?

 

I'm trying to create a simple schedule without having to manually calculate start and end dates.

1 answer

1 accepted

1 vote
Answer accepted

Hi @Lucas Scheer and welcome to the Community!

Not as far as I know. Auto-scheduling is a helper tool that - as you rightfully point out - considers a lot of things when creating a schedule. You probably have already found this support article describing a.o. those factors.

There is only a very limited bit of configuration you can do, as described in this support article: determine if you want to override values already present in existing issues or not.

Hope this clarifies! 