Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Come for the products,
stay for the community

The Atlassian Community can help you and your team get more value out of Atlassian products and practices.

Atlassian Community about banner
4,557,770
Community Members
 
Community Events
184
Community Groups

How do I set up a Start-to-Start Dependency in Advanced Road Maps?

How do I set up a Start-to-Start Dependency in Advanced Road Maps? Using Jira Cloud Based.

 

1 answer

1 vote
Ravi Sagar _Sparxsys_
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
Aug 09, 2021

Hi @Jeanne Higgins 

You cannot have that constraint on the issues based on Start-to-start dependencies. The way Advanced Roadmap dependencies work is Finish-to-Start where issues will be planned/started only when the predecessors have finished.

However you are free to plan the issues the way you want. Advanced Roadmap will suggest a schedule for you but you can always change it - for instance plan the issues in the same sprint and rank them together. The plan might give you warnings but you can ignore them.

Ravi

Ravi Sagar _Sparxsys_
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
Aug 09, 2021

..and you can configure dependent issues to be schedule concurrently instead of sequentially, but this will impact the whole plan.

What if you really are not using sprints?

How do you do "and you can configure dependent issues to be schedule concurrently instead of sequentially, but this will impact the whole plan" This?