How can I get velocity chart against a sprint? the issues are not estimated in story points but hour

kalyani gupta June 26, 2018

How can I get velocity chart against a sprint? The issues are not estimated in story points but hour.

When we go to velocity chart report under any project, the following message is displayed:

"There are no available sprints for this board." 

1 answer

0 votes
Tarun Sapra
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
June 26, 2018
Tarun Sapra
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
June 26, 2018

https://jira.atlassian.com/browse/JSWSERVER-9167

Your estimates should be on stories only then it will be taken into account as per the above open issue.

From the comments on above ticket

it affects Velocity chart since we estimate in sub-task level and the original estimate for parent is 0