Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Come for the products,
stay for the community

The Atlassian Community can help you and your team get more value out of Atlassian products and practices.

Atlassian Community about banner
4,556,856
Community Members
 
Community Events
184
Community Groups

Epics from Jira Project not visible in Plans

I have many epics defined in my Jira project, and all of them have connected stories. But when I look into plans some of the random epics even if they are In Progress does not appear on Plans.

The stories linked to those epics appear as issues without parent but I have checked many times that these stories have Epics linked.

Could not find a fix for this, tried different Plans settings but no effect, any resolution to this issue is highly appreciated.

1 answer

0 votes
Niranjan
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
Oct 05, 2020

Hi,

What is the data source of the plan? If that is board - What is the filter query used by the board? Does your filter query include Epics in it?