Can you show us what you have set up for the Swimlanes, please?
-
I only experiment with the TMP projects to try to answer questions. My expertise lies more with the CMP projects. We have TMP and CMP projects in our environment, many with the Done status. Our TMP projects say that the Done status is shared across multiple workflows, and the Delete button is disabled for deleting that…
-
Can you provide a screen image that shows us what you are seeing? Are the source projects all Company Managed projects, or all Team Managed projects, or a mix? When you say the swimlanes are defined through filters, do you mean you've set SwinLanes to Queries, and then defined filters to set the content of each swimlane?…
-
@chenxiwang Welcome to the community. Additionally, it is a best practice to remove access to the Delete Issue permission for all users except Jira administrators to reduce the chances of issues being deleted in error. Instead it is a better practice to have a "done" status that can be used for issues you would otherwise…
-
According to this document on Advanced Searching in Jira Data Center, Parent is a valid field to use in JQL if Sub-tasks have been enabled. https://confluence.atlassian.com/jiracoreserver/advanced-searching-fields-reference-939937719.html Are you using the Advanced Search and typing in your JQL, or the Basic Search and…
-
Hello @Jennifer Howard Are you using a board for a Company Managed project or a Team Managed project? It will say at the bottom of the navigation pane on the left. Also, is your project a Work Management (aka Business), Software, or Service Management project? This will show at the top of the navigation pane, below the…
-
Hello @Oliver Fowler Welcome to the community. Are you using Company Managed projects, Team Managed projects, or both? Are you defining a project-level automation or a global-level automation?
-
Hello @Clair Hur Welcome to the community. Are you talking about this app? Goals for Jira If so, according to the documentation "Only Closed issues are counted as progress on the goal, it means that progress charts will remain unchanged when someone starts progress on the issue and will drop only when the issue will be…
-
Can you elaborate on the challenges you are facing and the problem you are trying to solve?
-
Oops! Thanks for fixing my error @Bill Sheboy
-
If you want to see the entire backlog, you need a board for that. If you don't want to see the entire backlog and all sprints across all teams in one place, then you don't need a board for that. Note that there is no concept of "boards with boards underneath". There is no hierarchy to agile boards. Each board is its own…
-
Because you have included Sprints as part of your criteria, you backlog will always show as empty. An issue cannot be in both the Backlog and in a Sprint at the same time. If you want to see all the issues of all Statuses in the QUELL project, and you want to see the Backlog (issues not in sprints) plus all currently…
-
I would recommend using the Automation feature for this. You can create an Automation rule for the project that is triggered when an issue is created and has the Action to set the Assignee field. https://support.atlassian.com/jira-software-cloud/docs/automate-your-jira-cloud-processes-and-workflows/
-
Hello @Peter Cornelius Are you using a Team Managed project or a Company Managed project? It will say at the bottom of the navigation pane on the left. Are you using a Work Management (aka Business), Software, or Service Management project? It will say at the top of the navigation pane just below the project name. If you…
-
Hello @biboc It appears that you are working with a Team Managed project. With Team Managed projects it is the Parent field rather than the Epic Link field that is used in issues to identify their parent Epic. That is why the Epic Link field is not present. Also in Team Managed projects, they do not support editing that…
-
Hello @Eran Haskel Welcome to the community. It is not possible to convert a Team Managed project to a Company Managed project. The only option is to create a new Company Managed project and move the issues from the Team Managed Project to it.…
-
Oh, I see. I did not fully grasp your problem. I did not find anything in the REST API for the global priority value list other than GET commands. Nor do I see a way to delete multiple values through the UI.
-
Are you working with a Company Managed project or a Team Managed project? For a Company Managed project, there is a ... button in the upper right corner of the board display, and from there you would select Settings. For a Team Managed project you need to go to Project Settings > Board, and that will give you a screen for…
-
Do you mean for an individual Epic the percent of its child stories that are complete? Are you trying to get this information for multiple epics at once or one epic at a time? How do you want to determine percent complete; based on count of stories, or based on time estimates?
-
Are you talking about the built-in Priority field? The values of the built-in Priority field are managed in a global list which can be found at Admin Settings (the gear icon) > Issues > Priorities From there you can change the text labels, colors, icons, and ordering or Priorities, as well as deleting values. But the…
-
A Jira Administrator can change the owner of a filter to another user by going to the Gear button (next to their avatar) and selecting System, then Shared Filters. Search for the filter and then click on the ... button on the right next to it, and Change Owner will be an option for the Jira Admin. As for the filter not…
-
Hello @Richard Jones Welcome to the community. Are you an Administrator for the specific Kanban board you are trying to modify? Are you the owner of the filter on which that board is based? If you are not the owner of the filter, that explains why you had only the Save As option when modifying the filter itself. You need…
-
Hello @David I have a few fundamental process questions for you, so I can better understand your situation. Are development and testing handled by different people/teams? Is having the testing completed part of the definition of done for the ticket? If so, then it is totally appropriate that the ticket remain open until…
-
If you have modified the permission scheme to use Project Roles where you were previously using the User Groups, then you need to do one of the following 1. add the User Groups to the respective Project Roles in the relevant projects, or 2. add the individual users of each User Group to the respective Project Roles in the…
-
I am not seeing that in my Kanban Board displays. I don't have any Scrum boards. Are you sure that you don't have another filter applied (maybe a quick filter) that is reducing the actual tickets displayed to those assigned to only 5 users?
-
Hello @Deepika singh The issues that will appear in the boards is based on the filter the boards used. The filter is shown in the Board Settings > General tab. The issues themselves do not track in which board they are being displayed. If you want the issues to display in only one board or the other, you have to modify the…
-
I don't use JWME but from reading the documentation this validator (Field Required Validator) is only for validating that the field is not empty, and the Validator Scope is to define when the field is required (i.e. field is required for issues of type Story). I don't think this validator is for validating that a field has…
-
Some of those built-in fields are actually custom fields that have been added to the Jira product. Jira Core (Work Management) was the original core set of functionality. If you purchase Jira Software, you get Jira Core with a bunch of added features and fields. For instance Agile Boards functionality comes with Jira…
-
I'm not finding any built-in method to get the total estimated time for a planned sprint (before it is started). In another post I found a reference to using the third party app Adaptavist Scriptrunner to get something like that https://scriptrunner.adaptavist.com/latest/jira/jql-functions.html#_aggregateexpression There…
-
Due Date is not a custom field. It is a built-in field in Jira. Only user-defined custom fields will appear in the Custom Fields screen. You will notice that Description, Assignee, Summary, etc. (other built-in fields) also do not appear in the Custom Fields screen.