Comments
-
Hello @Beautiful Voice Welcome to the community. Are you working with a Company Managed project or a Team Managed project? For Company Managed projects you can add up to 3 fields to the card display in both the Backlog and on the Board through Board Settings > Card Layout. That option is not available in Team Managed…
-
It is not ideal, but I would recommend using just a scrum board. Planned work should be added to the sprint to fill half the normal velocity for the team. The remaining would be filled by unplanned work added to the sprint as deemed appropriate. Alternately you allocate some portion of the team to just the planned work,…
-
Hello @John Warde Welcome to the community. The fact that the parent issue shows up as a header line instead of a full card suggests that its Status is not the same as the Status mapped to that column. If the parent issue status was the same as that column, then it should show up as a card with its sub-tasks indented below…
-
Yo no hablo español. Estoy usando una aplicación de traducción. Espero que se traduzca esto claramente. Para que un problema se considere completado al final del sprint, el problema debe estar en la columna más a la derecha del tablero. Tampoco debe tener subtareas incompletas. ¿Sus problemas completados están configurados…
-
Hello @Raul Diez Welcome to the community. That is not a feature that is available natively in Jira. You would need to look for a third party app in the Atlassian Marketplace for that. If you go there and search for "jira search" that will give you several that you can explore to see if they have the feature you want.
-
What documentation did you use as a guide for executing your migration?
-
You can find several documents on the internet and posts in this community about the differences between Company Managed and Team Managed projects. Here is one: https://support.atlassian.com/jira-software-cloud/docs/learn-the-basics-of-team-managed-projects/ There is not an option/flag that changes a project from company…
-
Hello @Goon Yin Chew Welcome to the community. Here's the latest Jira Server version API document https://docs.atlassian.com/software/jira/docs/api/REST/8.22.0/ I don't see a "move issue" endpoint in it. Here's a change request asking for the functionality. https://jira.atlassian.com/browse/JRASERVER-61359 What problem are…
-
Hello @Divakar Ketha This is a community of Jira users, all using our own Jira instances. To get changes made in your Jira instance you will need to contact the Jira Administrators of your instance. If your instance is provided by your company but you don't know who the Jira Administrators are, I suggest you reach out to…
-
Because you are on the Free plan you won't be able to open a support case, but I suggest that you use the "Give feedback about Jira" option under Help (the question mark button near you avatar) to provide that feedback to Atlassian.
-
Can you provide a screen image that shows the new status in a workflow that is assigned to the workflow scheme that is assigned to this project? Does the filter for this board include all the issues in the project, or does it only get a subset of the issues in the project? If the latter, does it include the issues to which…
-
Hello @Mahlia Amanda Putri Welcome to the community. That is expected behavior. It currently is not possible to show sub-tasks as separate cards on the board. There is a change request for that here: https://jira.atlassian.com/browse/JWMCLOUD-17
-
Hello @[deleted] With Jira Standard and the native Basic Roadmaps you don't have the ability to change or add to the hierarchy for issues. You get only the native hierarchy which is Epics > general issues (Story, Bug, Task, etc.) > Sub-tasks With Jira Premium you would get Advanced Roadmaps natively, which does give you…
-
Hello @Edwin Lee This is a bit confusing. Because two sections showed in the column when you drag an issue to it, I assumed that there would be two statuses mapped to that column. Was there actually only one status mapped to that column? I was not suggesting removing a status from the column. I was suggesting removing the…
-
Hello @Edwin Lee The statuses that appear as sections in a column are statuses that are available in the workflow. To remove the section from the display, you have to remove that status from the workflow. I'd have to do an experiment to confirm, but it could be that you are seeing a status that applies to a workflow for…
-
Hello @amanda.wilson The lack of change is a known issue documented here: https://jira.atlassian.com/browse/JRACLOUD-72148
-
Hello @RC Welcome to the community. As you can see, neither of those options is available. The work around would be to select None, and then to set up Quick Filters that you could use to hide the cards, such as this: statusCategory!=Done or (statusCategory=Done and ResolutionDate>-8w)
-
This is a global setting for your Jira instance. It can be changed by Jira Administrators using the guidance in this document: https://support.atlassian.com/jira-cloud-administration/docs/configure-file-attachments/
-
@Lars Vilhelmsen @Jeremy Sherwood @Ana Vizcarrondo @Jatuporn @WajahatRahman Given that this is a user community, not a support portal, there is not a standard that Atlassian personnel are monitoring all the posts to provide answers. I recommend that you contact Atlassian Support directly by opening a support case…
-
Which completed sprint information are you asking about? If you delete a board, the reports that you accessed through that board are no longer available.
-
Hello @symeonidisfx Welcome to the community. For a Kanban board there are options that automatically stop displaying issues in the "done" column when they reach a specified age. For a Kanban board on a Team Managed project, issues that have been "done" for 14 days will no longer be shown on the board. This can't be…
-
Hello @sushree sharmila mallick Welcome to the community. This is a user community comprised of people who use Jira. You can get advice here from other Jira users and administrators. If you want to get assistance directly from Atlassian you will need to open a support case via https://support.atlassian.com/contact/ When a…
-
Are you working with a Team Managed project or a Company Managed project? Can you show us a screen image of the Columns page where statuses are mapped to columns? For a Kanban board the Backlog screen is divided into two sections; the Backlog section and the "other" section. The label for the "other" section depends on…
-
Your email may have gotten blacklisted on the Atlassian side. You (or your Jira Administrators) should open a support case directly with Atlassian to find out if that is the case and get it resolved if it is.
-
Manually created boards are designed to work with Company Managed projects. When a manually created board is displaying data from a Company Managed project you can click on an Epic in the Epics pane and the list of issues will be filtered to show the child issues of that Epic. That is the same behavior you see in an…
-
Hello @April Morris Welcome to the community. What are you referencing specifically when you say "the Project queue"? Can you provide a screen image of what you're viewing, and a screen image of an issue you would want to not see in the list (blacking out confidential info, of course)? I also note that the doc you…
-
Hello @Cedric Oeldorf Welcome to the community. Backlog Prioritisation is not a native feature in Jira Cloud. I believe you are getting that feature from a third party app that has been added to your instance. Can you check with your Jira Administrators to find out which third party app is being used and provide that…
-
Hello @Jesse Maxwell In order to accomplish that you will have to switch from using the Simplified Workflow to using a customized workflow. As per this article, the design of a Simplified Workflow is intended to allow issues to move freely from one status to another. After switching to use a customized workflow you can add…
-
If you are using the native email handler functionality, then the sender of the email must be a licensed Jira user with access to create issues in the destination project, if the destination project is a Software project. If you want unlicensed users to be able to create issues by sending an email, then the destination…
-
Hello @LeCour.Antoine Welcome to the community. The message "x completed issues" that you see when you close the sprint reflects the number of issues in the right-most column which do not have any open Sub-tasks. An issue is considered complete at the end of the sprint if the status of that issue is mapped to the board…