You said you set up a Service Management project, but your image shows that it is a Business project (a.k.a. Work Management). I'll answer accordingly. You can add the Work Management project Calendar view to a Software project by using "Add Shortcut" in the navigation pane and manually creating the Calendar shortcut.…
-
I found this response in another post: This option to set priority scheme per project is only an option for the server version of Jira. This option is currently under consideration for Jira Cloud. See the link below. https://jira.atlassian.com/browse/JRACLOUD-3821
-
Hello @Alejandra Martin Welcome to the community. It is not currently possible to specify that the new project to be created during CSV Import be a Team Managed project. You will have to create the Team Managed project first in your Jira instance and then import the issues. Note that there are other problems with trying to…
-
A Project Administrator for the project can use the Import Issues from CSV process to import a single issue that has all 20 components specified in it. When this is done by a Project Admin, the import process will create a Component for each value that is not already a Component for that project.…
-
The image that you are showing is indicating that the Board feature is already on and cannot be disabled. You should see that "Board" is already listed in the navigation pane on the left, and if you click on it the Board will display. If that is not the case, in your navigation pane at the top below the project name does…
-
Here is the change request for that in Atlassian's backlog. You might want to Vote for it. https://jira.atlassian.com/browse/JSWCLOUD-18377
-
Are you using Team Managed projects, Company Managed projects, or both? Do you have only the Jira Software product or also the Jira Service Management project? You can create a board from a saved filter that retrieves issues from all projects (or a specific list of projects) on the system. There are caveats: 1. If you…
-
Go to the ... button in the upper right corner and select Board Settings. Then select the General screen. Review the filter that is being used to select issues for your board. Is does it exclude Epic types of issues? Can you show us the filter?
-
Use the Notification Scheme and Workflows. In the workflow transitions make sure they are firing a Generic Event or a Custom Event. The in the Notification Scheme set Reporter as a person to be notified on the type of event being fired in the workflow transitions.…
-
For a Company Managed project, the fields available for issues and the ones that are actually displayed on the screens are managed through Schemes that can be edited only by Jira Administrators. Schemes are then associated to projects. Schemes can be shared among many projects, and any change to the Scheme will affect all…
-
When you are viewing the board and you click on Active Sprints, is only one sprint showing for the board? When you go to Reports > Burndown Chart, can you select the completed sprint and confirm that in the Event table below the last Event listed is "Sprint Ended"?
-
The first question - is this a Team managed project or a company managed project - can be answered by looking at the bottom of the navigation pane on the left when you are viewing the project. There it will say Team Managed or Company Managed.
-
And at the top of the navigation pane, can you confirm that it says Software below the name of your project?
-
Hello @Jean Samsel Welcome to the community. Against which field/field-type are you trying to set the criteria?
-
This appears to be a duplicate of another post that has a response: https://community.atlassian.com/t5/Jira-Software-questions/Approving-Tempo-timesheets/qaq-p/1887306
-
@Arthur Harutyunyan I see that you marked this post as Answer Accepted. Is your issue resolved? If so, what was the issue? Was it what @Gaurav suggested and not all statuses were mapped to columns?
-
Hello @Kelsey Reed Welcome to the community. Are you working with a Team Managed project or a Company Managed project? It will say at the bottom of the navigation pane on the left. And at the top of the navigation pane, can you confirm that it says Software below the name of your project?
-
Hello @Ijlal Nasir Welcome to the community. I don't think there is a way to do this, but I believe this is the change request in Atlassian's backlog for it. https://jira.atlassian.com/browse/JSWCLOUD-17803 There was also discussion of the adaptive sizing with scroll bar vs. no scroll bar in this thread, and a few…
-
You cannot set edit permissions on individual issues, but you can restrict access to edit fields by creating a Workflow Transition with an attached screen that presents those restricted fields for editing. This methodology is discussed in this post:…
-
In the image you posted, you have a status named "Planned" rather than "To Do". If you applied that exact workflow to your existing project where you have the "To Do" status, that could be part of the problem. When you are trying to more the issues in the project where they won't move: 1. What is happening when you try to…
-
When you select the Epic Burndown report, I suspect the whole message you are seeing is this. Am I correct? If so, notice that it says there are no epics on the board. You can't create an Epic Burndown report if there are no Epics in the board. You must first have Epics in the board. When you click the button to Add Epics,…
-
Epic Link field is not used in Team Managed projects. Have you confirmed that this rule works for a Team Managed project?
-
@Nastya Polyshuk Welcome to the community. Simply click in the Labels field and click the X for the label you want to remove.
-
Is this for issues in a Team Managed project or a Company Managed project? Is the field not displaying on the screen, or is the field present but empty? If the field is not showing on the screen, have you confirmed that it is not simply hidden because it is empty? Check the More Fields list and the Configure options. If…
-
Where does this rule link the child issues to the Epic?
-
Does the Epic exist in a Team Managed project or a Company managed project?
-
For your second filter the filter would be createdDate =< "2021-12-01" AND resolved >= "2021-12-01"
-
Hello @Arthur Harutyunyan Can you show us the actual filter on the board? Can you show use an image of the Label values in issues from the next-gent project? What is the issue type of the missing issues?
-
Hello @Shabbir Hassan Welcome to the community. For tickets that carried forward into the month: There is not a built in time stamp for the Closed Date for issues, but there is one for the Resolution Date, which is often the same thing. You could use this filter createdDate < startOfMonth() and (resolutiondate is empty or…
-
Looking at the info in the pricing screen, you have to purchase it for all users.