Got initial response on this from @Mark Segall about Plans and Adv Roadmaps.
Correct Plans and Advanced Roadmaps are one and the same.
When you create a new issue type that is expected to reside above the Epic in the issue type hierarchy such as Initiative, you have a choice in how you want to employ it. Factors to think about as to whether Initiatives should reside with their child issues or centralized in their own project:
- Governance - Do you want to limit who can create, transition, resolve these types of issues?
- Scope - Will the child issues reside on multiple projects?
If the answer is "Yes" to either of these questions, it makes sense to use a central repository for managing the Initiatives. From there, you would just need to be sure that you're adding that project to your Plan's issue source.
@Mark Segall We have multiple Modules or Independent components being developed. So per JIRA limitation we are thinking to have Epic -> Story -> Task hierarchy in each project which is per module / component we are building. At org level / bigger product theme - we would like to map multiple EPICS from multiple projects to Initiative at the top - platform / Org level.
In such case where should we keep the initiatives?
create a new project and add just initiatives in it or is there a JIRA space/repository at top, above projects where we can keep adding initiatives and link Epics from projects to Initiative?