We're using the IDE connector from Eclipse 3.7 to work with JIRA issues. Everything seems to work well with one major problem: if I check the box to Log Work Done and enter time spent (or let it enter a value for me based on how long the task was active), the time is uploaded to Jira, but THE ISSUE IS ALSO MARKED AS FIXED. I have to go into Jira, mark it complete, then re-open it.
The task is still marked as "In Progress" even though the resolution is now "Fixed". I didn't modify anything else in the task except to add time, so I definitely did not accidentally mark it Fixed.
Any ideas? Could there possibly be something up with the Jira server that would do this? Or is this something wrong with the connector?