Are you sure the board is configured to use Story Points for estimation? If so, it looks like the estimates are empty.
yes - the board is set for Story Points as estimation.Screen Shot 2015-07-07 at 12.12.17 PM (2).png
It does work in the Backlog however.
Screen Shot 2015-07-07 at 12.16.05 PM (2).png
Was there a resolution on this? I have the same issue.
I had the same problem. In the time tracking you must check none.
Selecting option "None" for the "Time Tracking" in the "Estimation" tab of the Board settings, as was suggested by @Iason Filippopoulos, helped me as well