We are just now starting to use Portfolio to manage a few projects and initiatives, but we haven't been able to correctly create a plan with linked Epics.
Historically, our Jira installation has its issue linking configured with the default:
- Outward: Depends on
- Inward: Is depended on by
Now that we have portfolio installed, we noticed that it's treating outward/inward relations in reverse. I noticed from this forum that the concept of issue linking is confusing (example).
In our case, Portfolio is only able to calculate Schedule dates correctly among dependent Epics when we reverse the dependency. We could workaround this by changing the names in the link description, but that would completely mess with the entire issue history we have.
I would appreciate any ideas on how to get around this or how to fix it.
EDIT: The official Jira documentation for issue linking provides examples that show the same link direction we have.
https://confluence.atlassian.com/adminjiraserver073/configuring-issue-linking-861253998.html