Hi there
I have a Jira Sructure set up as a Gantt chart. I had edited the configuration so that it is usinga specific working calendar that has our Christmas shutdown days as exceptions.
This is reflected in the duration of the tasks in the Gantt chart (i.e. one going across the Christmas break is now extended), however I cannot visually see this as a grey background on the Gantt chart, like weekends are shown.
To the external viewer it's not obvious that we're closed over Christmas on the Gantt chart, so it just looks like those tasks are massively long.
How can I make the Gantt chart visually show the exception days in grey background?