Hi all,
Can we link the start of a new Sprint to end of old Sprint? Can we put a control in such a way that, unless the old Sprint is closed the new Sprint can not start?
Hello,
You should disable the parallel sprint feature:
https://confluence.atlassian.com/jirasoftwarecloud/using-parallel-sprints-797737030.html
Thanks Alex! This would help greatly.
You are welcome! If my answer helped you, kindly mark my answer as accepted.
It looks like you're new here. Sign in or register to get started.