I have transitioned one issue to Done. On the release, it shows up as In Progress. Any idea why? Using the system default workflow for Scrum projects.
Your "done" status appears to be in the yellow "in progress" status category. I'd move it into the green "done" status category, and that should fix the report.
Also make sure the Resolution field is set.
How do you move it to green? I've got its status set to done on the board.
The resolution field is set to "Done". The issue looks like this
As @Nic Brough -Adaptavist- wrote, the DONE status is not mapped to "green" in the status category.
Go to Admin -> Issue -> Status, find the status and edit it, changing the status category to "done"
Thanks. That did the trick.