Hi,
I'm struggling with the right way to handle canceled issues in the sprint.
I tried several options, but didn't find a way that will reflect the truth.
1. If I put the canceled status in a mapped column, or the un-mapped, then the reports are fine (velocity, burn down, sprint report), but at the end of the sprint the issue will be transferred to the next sprint or back to backlog.
2. If I am removing the canceled issues from the sprint, then the burn down report doesn't count them as committed.
3. If I am filtering out the canceled issues from the board's filter - again the reports are not taking them into account.
How are you handling it?
Will be glad to hear some ideas.
Thanks,
Orit.