All,
I would like to enable the Estimated Hours for Sub-Task , Currently i can find only log hours.
On Story level the estimated hours is available.
Will i get a navigation steps for enabling the Estimated Hours for Sub-Task
You need to add "time tracking" to the create and edit screens for the sub-tasks.
Bear in mind that this will not be used in any Scrum calculations.
How do i do that can you share me the navigation
go to project>settings>screens>edit option aligned towards right corner >click on concerned screen>add time tracking
I tried it i could not able to find the sub task screen itself on Screens page
you are sharing jira settings page
go to dashboard>projects>select the concerned project>then settings>screens
then share that images then i could help you
like this
Thank you so much i have enabled
accept the answer