Hi guys, so we use jira queries in confluence for reporting purposes and it works really well. Im just trying to optimise how we create the reports as currently there are a lot of dates to edit weekly and if ones forgotten then the numbers are out of sync.
The current query is
project = A1 status changed TO ("In Implementation") DURING ("2018-07-29", "2018-08-04") AND "epic link" = EMPTY and assignee not in (joe.bloggs) OR status changed TO ("In UAT") DURING ("2018-07-29", "2018-08-04") AND "epic link" = EMPTY and assignee not in (joe.bloggs) so I've had to duplicate the query after the OR function, what im trying to do is something like
project = A1 AND (status changed TO ("In Implementation") OR status changed TO ("In UAT")) DURING ("2018-07-29", "2018-08-04") AND "epic link" = EMPTY and assignee not in (joe.blogs)So here ive not duplicated the full query just the things that differ meaning there is only one date per query. the above doesnt work but I wanted to know if anybody knew of anything similar to allow this to be done?