Hi
I would like to be able to edit a Jira issue and adjust the Remaining Estimate whilst leaving the Original Estimate blank. This is so that I can accurately see which date the release is tracking to without adding in an original estimate for an issue that has come into queue mid-release. If I try to do this Jira copies the value for the Remaining Estimate to the Original Estimate when I save. If I put 0 hours in for the original estimate, that messes with my time tracking report as it thinks all these issues were wildly under-estimated, when in fact I just want them excluded.
I'm not using Legacy Mode for time tracking.
Any ideas?