I have downloaded both ScriptRunner and Automation for Jira as I am trying to automatically update the end date of a story, if its subtask has an end date exceeding its own.
For example, I have created a story which will run from 1st January to 20th January. Within this story, I have created a subtask which runs from 10th January to 18th January. Now if the subtask overruns and I increase the end date to 24th January, I want the story to automatically update to have an end date of 24th January, as opposed to its original end date of 20th January.
Does anyone know how to do this?