Hi,
What is the best practice to apply during sprint planning for employee's vacations?
I can think of 2 options:
1. Create a vacation task with the right amount of sp.
2. Create a sprint with smaller velocity.
The reason I think about option1 is because i want to have a velocity for that sprint that could later be used in the average calculation with other sprints to discover the average velocity for full week.
What do you think?