Hi,
We have to set up a Project in JIRA where we will have multiple tracks (SCRUM Teams) working on a single list of Master User Stories. Each Scrum team will have their own tech stories/tasks associated with Master User Stories and each team will have their own Sprints. There are some level of dependencies across Scrum teams and hence the sequencing of Sprints & User story selection within the Sprints need some level of cross team planning.
Looking for advice/guidance on how should we set up this project in JIRA so that
1. Each Scrum team will have their own backlog, Sprint Board, Sprint Cycle - Multiple Scrum Board and multiple Sprint-1/2/3 etc.. for different Scrum teams within same Project
2. Link the Tech stories within each Scrum to the Master User Stories and get the point-in-time view of the Master User stories at Project level
3. Generate Reports/metrics (Velocity, Burn down Chart at Scrum team level as well as Project level
Thanks
Anirban