Scenario:
1) I have created Story with Original Estimate of 4w
2) I have created Subtask 1 Original Estimate of 2w
3) I have created Subtask 2 Original Estimate of 2w
4) I log work on Subtask1 for 1 w
5) Subtask1 Remaining Estimate shows 1w which is correct
6) Story Remaining Estimate still shows 4w
Please suggest why log work is not rolling up to Parent Story.